Indiana Faces a Data Center Backlash


Article by Matthew Zeitlin: “Indiana has power. Indiana has transmission. Indiana has a business-friendly Republican government. Indiana is close to Chicago but — crucially — not in Illinois. All of this has led to a huge surge of data center development in the “Crossroads of America.” It has also led to an upswell of local opposition.

There are almost 30 active data center proposals in Indiana, plus five that have already been rejected in the past year, according to data collected by the environmentalist group Citizens Action Coalition. GoogleAmazon, and Meta have all announced projects in the state since the beginning of 2024.

Nipsco, one of the state’s utilities, has projected 2,600 megawatts worth of new load by the middle of the next decade as its base scenario, mostly attributable to “large economic development projects.” In a more aggressive scenario, it sees 3,200 megawatts of new load — that’s three large nuclear reactors’ worth — by 2028 and 8,600 megawatts by 2035. While short of, say, the almost 36,500 megawatts worth of load growth planned in Georgia for the next decade, it’s still a vast range of outcomes that requires some kind of advanced planning.

That new electricity consumption will likely be powered by fossil fuels. Projected load growth in the state has extended a lifeline to Indiana’s coal-fired power plants, with retirement dates for some of the fleet being pushed out to late in the 2030s. It’s also created a market for new natural gas-fired plants that utilities say are necessary to power the expected new load.

State and local political leaders have greeted these new data center projects with enthusiasm, Ben Inskeep, the program director at CAC, told me. “Economic development is king here,” he said. “That is what all the politicians and regulators say their number one concern is: attracting economic development.”..(More)”.